Lift Stations for Wastewater OperatorsPage 15 of 72

Module 2 ยท Pumps, Level Controls, and Operating Cycles

Lead, Lag, and Alternation

The lead pump is the first pump called when the wet-well level rises. A lag pump starts when the lead pump cannot keep pace or when the level reaches another control point.

Wet well with one pump running, then both pumps running at higher level

Alternation changes which pump becomes lead for the next cycle. This can distribute run time and starts between available units. Balanced use also helps reveal whether both pumps can perform the duty.

Unequal hours do not always mean a fault. Different pump sizes, programmed sequences, maintenance outages, or peak-flow operation may create an intended difference. Compare results with the station's control description.

If a pump is unavailable, staff must understand how capacity and alternation are affected. Record the change and follow the plant's reduced-capacity and notification procedures.

Exam Need to Know

  • The lead pump starts first; the lag starts if lead cannot keep up.
  • Alternation switches which pump leads each cycle to share run time.
  • Pump hours that differ don't always signal a fault.

Exam area: Equipment