Two clarifiers normally receive 50% of plant flow each. During a four-hour sludge-pump repair, Clarifier 1 must be reduced to 30% of normal plant flow. Clarifier 2 can accept 10% more plant flow, and influent can be reduced by 10%. Which plan meets all three limits?
Answer: A. Route 90% total as 30% to C1 and 60% to C2
Primary effluent TSS rises only during the first hour of morning flow. Blanket depth stays normal, sludge pumps meet capacity, and influent sampling shows a short surge of fine solids. A polymer trial improves capture but also increases primary-sludge mass by 25%, leaving little digester reserve. What is the best next evaluation?
Answer: C. Test surge-paced feed against solids capacity